Weekly works schedule
Week ending 15 December 2017

The Weekly Works Schedule will recommence later this week.

Proposed schedule this week Work achieved this week Proposed schedule next week
Bridge construction/maintenance
  • Austral Eden Outer Road - Anderson's Bridge replacement

    Place culverts
    Backfill
  • Austral Eden Outer Road - Anderson's Bridge replacement

    Place culverts - Completed
    Backfill - Completed
  • Austral Eden Outer Road - Anderson's Bridge replacement

    Place and compact road base
    Road expected to re-open on 20/12
Flood mitigation maintenance
  • Drains Maintenance
    Glenrock Drain - weed spraying
  • Drains Maintenance
  • Glenrock Drain - weed spraying - deferred
  • Routine inspections and maintenance
Drainage/kerb/footpath/drainage maintenance and replacement
  • West Kempsey area - Remove and replace k&g Pour kerb and gutter

  • - James Carney Crescent
    - Mitchell Avenue
    - Eric Kennedy Street
  • West Kempsey area - Remove and replace k&g Pour kerb and gutter

  • - James Carney Crescent - completed
    - Mitchell Avenue - completed
    - Eric Kennedy Street - completed
  • West Kempsey area - Remove and replace k&g Pour kerb and gutter

  • Restoration/sealing of shoulders will be undertaken as resources allow.
Bitumen road resealing/maintenance
    Pothole patching

    - Maria River Road
    - Collombatti Road
    - Nulla Nulla Creek Road
    • Pothole patching

      - Maria River Road - completed
      - Collombatti Road - completed
      - Nulla Nulla Creek Road - completed
  • Pothole Patching

    - Access roads
    - Carparks
    - Hat Head streets
Bitumen road construction/rehabilitation
  • Stuarts Point Road (Mighell Road to Browns Road)
    - Install guardrail (contractor)
  • South Street, South Kempsey - rehabilitation
    - Asphalt surfacing - bridge to West Street(weather permitting)
  • South West Rocks Road (Pola Creek Road to Red Hill Lane) - rehabilitation
    - Drainage works
    Widen shoulders
    Place pavement overlay
  • Stuarts Point Road (Lukes Lane to Mighell Road)
    Final coat seal (weather permitting)
  • South West Rocks streets
  • Lawson St - Final seal (expected 8/12)
    Entrance St - Final seal (expected 8/12)
    Wentworth St - Final seal (expected 8/12)
    Jubilee St - Final seal (expected 8/12)
    Elizabeth St - Final seal (expected 8/12)

  • River Street/North Street intersection
    Asphalt surfacing - bridge to West Street (weather permitting)
  • Stuarts Point Road (Mighell Road to Browns Road) - Widening and rehabilitation
    Rehabilitation:
    - Install guardrail (contractor) - completed
  • South Street, South Kempsey � rehabilitation
    Asphalt surfacing - bridge to Akubra - completed
    Balance deferred for completion with South Street extension
  • South West Rocks Road (Pola Creek Road to Red Hill Lane) - rehabilitation
    Widen shoulders - completed
    Place pavement overlay - completed
  • Stuarts Point Road (Lukes Lane to Mighell Road)
    Final coat seal - commenced 9/12, not completed (rain)
  • South West Rocks streets
  • Lawson St - Final seal - not started
    Entrance St - Final seal - not started
    Wentworth St - Final seal - not started
    Jubilee St - Final seal - not started
    Elizabeth St - Final seal - not started
    All deferred due to contractor plant breakdown - to be reprogrammed for February as contractor has no availability before new year.

  • River Street/North Street intersection
    Asphalt surfacing - bridge to West Street - completed 13/12
  • South West Rocks Road (Pola Creek Road to Red Hill Lane) - rehabilitation
    - Prepare for seal
    - Bitumen seal
  • Stuarts Point Road (Lukes Lane to Mighell Road)
    -Complete final coat seal planned for 15/12
  • River Street (Elbow Street to North Street)
    - Final coat seal planned for 18/12 (weather permitting)
  • North Street (River Street to Warwick Avenue)
    - Final coat seal planned for 18/12 (weather permitting)
Gravel resheeting
  • Collombatti Road (end bitumen to Chain o Ponds Road)
    - Prepare and shape for resheeting
  • Collombatti Road (end bitumen to Chain to Ponds Road)
    - Prepare and shape for resheeting - 50% complete
    - Place, compact and trim gravel - 40% complete
    - Balance deferred until 15/1/18
  • No gravel resheeting works proposed
Gravel road maintenance grading
  • Maria River Road
    Armidale Road
  • Maria River Road - completed
    Armidale Road - 20% complete
    Swan Road - completed
  • Armidale Road
    Point Plomer Road
    Chain o Ponds Road
Roadside slashing
  • Crescent Head Road
    Macleay Valley Way (Kempsey to Frederickton
    Summer Island Road
    South West Rocks Road
  • Crescent Head Road - 50% complete
    Macleay Valley Way (Kempsey to Frederickton) - completed
    Summer Island Road - completed
    South West Rocks Road - 20% completed
  • Crescent Head Road
    South West Rocks Road
    Hat Head Road
Other works
  • Central Kempsey Sewer Treatment Plant Access road and site earthworks
    -Tidy up and seed all verges and drains
  • Elbow Street upgrade (refuge side islands)
    - Form and pour islands
  • Elbow Street upgrade (refuge centre islands)
    - Plant trees
  • South Street - extension from West Street to Gowings Hill Road (contractor)
    - earthworks
    - Import and place selected fill layer
    - Import and place subbase (western end)
    - Traffic switch to new alignment (west end)
  • Lachlan Street, South Kempsey (street upgrade)
    Stage 1 - West side (Carri Street to Nicholson Street):
    - Backfill kerb and gutter to Carri Street
    - Pour pedestrian refuge
    - Form and pour driveways
  • Gregory Street Pedestrian Refuge (at Gordon Young Drive)
    - Install handrail
    -Install linemarking
  • Little Rudder Street - (Replace stairs to Macleay Valley Way)
    - Construct stairs
  • Access to Back Creek Beach - SWR Lions Club project (contractor)
    - Awaiting installation of handrail and fencing
  • Riverside Park wharf (contractor)
    - Install deck
    - Install handrails
  • Jerseyville Boat Ramp Floating Pontoon (contractor)
    - Awaiting delivery of pontoon and gangway
  • Macleay Valley Way, Clybucca (at Plummers Lane)
    - concrete pavement repairs
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    Tidy up and seed all verges and drains - completed
  • Elbow Street upgrade (refuge side islands)
    - Form and pour islands - completed
  • Elbow Street upgrade (centre islands)
    -Plant tress- completed
  • South Street - extension from West Street to Gowings Hill Road (contractor)

    Earthworks - 70% complete
    Import and place selected fill layer - 80% complete
    Import and place subbase - 20% complete
    Traffic switch to new alignment (west end) - completed
  • Lachlan Street, South Kempsey (street upgrade)
    Stage 1 - West side (Carri Street to Nicholson Street)
    :

    Backfill kerb and gutter to Carri Street - completed
    Pour pedestrian refuge -completed
    Form and pour driveways - completed
    Form and pour footpaths - completed
    Backfill and place soil to grassed areas - 75% complete
  • Gregory Street (at Gordon Young Drive)
    Pedestrian refuge:
    Install handrail - not started (awaiting materials)
    Install linemarking - completed
  • Little Rudder Street
    Replace stairs to Macleay Valley Way:
    - Construct stairs - 75% complete - no progress
  • Access to Back Creek Beach - SWR Lions Club project (contractor)
    - No progress
  • Riverside Park wharf (contractor)
    Install deck - lower decks/ramps completed
    Install handrails - 90% complete br/>
  • Macleay Valley Way, Clybucca (at Plummers Lane)
    concrete pavement repairs - failed pavement removed and replaced with flexible pavement - sealing completed
  • Nulla Nulla Creek Road - bridge replacement
    Bitumen seal road over new culvert - completed
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    No further work planned until 5/2
  • Elbow Street upgrade (refuge side islands)
    - Form and pour islands
  • South Street - extension from West Street to Gowings Hill Road (contractor)
    Earthworks
    Import and place selected fill layer
    Import and place subbase
    Work will cease on 22/12 and resume on 8/1
  • Lachlan Street, South Kempsey (street upgrade)
    Stage 1 - West side (Carri Street to Nicholson Street):

    Backfill and place soil to grassed areas
    Asphalt surfacing planned for 19/12 (weather permitting)
    Work will cease on 21/12 and resume 29/1
  • Gregory Street (at Gordon Young Drive)
    Pedestrian refuge:
    - Install handrail - expect completion by 21/12
  • Little Rudder Street
    Construct stairs - expect completion by 21/12
    - construct stairs
  • Access to Back Creek Beach - South West Rocks Lions Club project (contractor)
    - Awaiting installation of handrail and fencing
  • Riverside Park wharf (contractor)
    - install handrails
  • Macleay Valley Way, Clybucca
    - concrete pavement repairs - no further works planned until 5/2

Further works information